Stormwater is the compliance program that California contractors and owners most often treat as paperwork until a Regional Water Board inspector shows up after a rain event and finds muddy water leaving the site. The Construction General Permit is not a Cal/OSHA rule, but it carries its own inspection regime, its own credentialed roles, and its own enforcement, and a project that disturbs an acre of soil cannot legally start without it. As a Qualified SWPPP Developer, I spend a fair amount of time explaining to project teams what the permit actually requires and what an inspector expects to see. This article covers the threshold, the risk levels, the QSD and QSP roles, and where projects most often get in trouble.
Who Needs Coverage
The current permit is State Water Board Order 2022-0057-DWQ, adopted September 8, 2022 and effective September 1, 2023. It covers construction and land disturbance activities that result in a disturbance of one or more acres of soil. It also covers projects that disturb less than one acre if they are part of a larger common plan of development or sale that in total disturbs one or more acres. That second clause surprises people. A single-lot builder in a subdivision graded as one project is part of the common plan, and so is a phased campus expansion.
Linear underground and overhead projects, such as pipelines and transmission corridors, are covered under their own attachment and can be segmented into separately regulated sections.
Coverage is obtained by submitting Permit Registration Documents through SMARTS, the State Water Board’s online system: the Notice of Intent with the risk level determination, the site map, and the SWPPP itself. An applicant has coverage and may begin construction activity upon receipt of a WDID number generated by SMARTS. Not upon submittal. Grading before the WDID issues is one of the cleanest violations a Regional Board can write.
Risk Levels and What They Mean
The permit sorts projects into Risk Level 1, 2, or 3 using the worksheet in Attachment D.1. Two factors drive it. Sediment risk is calculated from the site’s erosion potential, expressed in tons per acre: low is less than 15, medium is 15 up to 75, and high is 75 or more. Receiving water risk is high if the project discharges to a water body listed as impaired for sediment or with a sediment-related TMDL, or one with certain sensitive beneficial uses, and low otherwise. The two are combined in a matrix. In practice, a flat site draining to an unimpaired channel is Risk Level 1, a highly erodible slope above a sediment-impaired creek is Risk Level 3, and most of what I see in the Los Angeles basin lands in Risk Level 2.
Risk level matters because it sets the monitoring burden. Risk Level 1 sites conduct visual inspections and monitor for non-visible pollutants but are not required to sample pH and turbidity. Risk Level 2 and 3 sites must collect stormwater grab samples for pH and turbidity from each discharge location once per 24-hour period of each qualifying event during active discharge. The numeric action levels in the 2022 permit are a pH range of 6.5 to 8.5 and turbidity of 250 NTU. Exceeding an action level is not automatically a permit violation, but it obligates the discharger to find the source, implement corrective action immediately, and keep iterating until the discharge is back within the action level. Risk Level 3 sites face receiving water monitoring, with upstream and downstream samples, when a discharge exceeds 500 NTU or falls outside a pH of 6.0 to 9.0, with results due within 10 days of the event.
The QSD and the QSP
The permit creates two credentialed roles, and they are not interchangeable.
- Qualified SWPPP Developer (QSD). The QSD develops the site-specific SWPPP and amends it as needed. Under the 2022 permit, the QSD must assess how the construction activities will affect sediment transport and erosion, revise the SWPPP when inspections, sampling data, or QSP comments identify problems, and inspect the site twice a year, once between August and October and once between January and March. A QSD must hold a qualifying professional license or certification in addition to completing the State Water Board’s training and exam.
- Qualified SWPPP Practitioner (QSP). The QSP is the field role. The QSP verifies that every BMP in the SWPPP is implemented, correctly installed, inspected, and maintained, reviews the work of trained delegates who do routine inspections and sampling, and must personally inspect the site at least once every calendar month. The QSP credential also requires completing the approved training and exam.
The gap I see most often is a project with a SWPPP stamped by a QSD who never returns, and no QSP named at all. The superintendent does the weekly inspection form from the trailer. Under the permit, routine inspectors and samplers must be the QSD, the QSP, or someone trained by the QSP, and the QSP must be reviewing their work. If nobody on the project is a QSP, that chain does not exist.
Inspections: Weekly and Around Every Storm
Attachment D sets the inspection schedule for all three risk levels:
- Routine visual inspections at least weekly.
- A pre-storm inspection within 72 hours before any weather pattern forecast to have a 50 percent or greater chance of 0.5 inches or more of rain in a 24-hour period. The permit allows this to extend up to 120 hours ahead where extended forecast data is available.
- During a qualifying event, an inspection at least once every 24-hour period, with the event extended for each subsequent 24-hour period forecast to have at least 0.25 inches.
- A post-storm inspection within 96 hours after each qualifying event if 0.5 inches or more was actually measured.
Each inspection must be documented, showing what was found, what was corrected, and when. A form that says “all BMPs OK” in the same handwriting every week for six months is not credible, and inspectors know it.
Reporting and Closing Out
Annual reports are certified and submitted through SMARTS by September 1 for the July 1 through June 30 reporting year, whenever a WDID has been active for at least 90 days in that period. Sampling results and any Numeric Action Level Exceedance Report requested by the Regional Board also go through SMARTS. When the project is done, the discharger files a Notice of Termination. The Regional Board will accept it only when the site meets the permit’s completion conditions, including final stabilization of all disturbed soil. The simplest route to final stabilization is the 70 percent method, which requires permanent vegetative cover evenly established over 70 percent of all disturbed and exposed soil that is not paved or built. Until the NOT is accepted, the permit, the inspections, and the annual fees continue.
Regional Water Board Enforcement
Enforcement comes from the nine Regional Water Quality Control Boards, not the State Board, and the pattern is predictable. Inspectors visit after significant rain, look at the discharge points and the downstream channel, then ask for the SWPPP, the WDID, the inspection records, and the sampling data. Sediment-laden discharges, failed perimeter controls, unstabilized stockpiles, and tracked-out mud are the physical findings. Missing pre-storm inspections, no QSP, no sampling on a Risk Level 2 site, and a SWPPP that does not match the site are the paperwork findings. Liability under the Clean Water Act and the Porter-Cologne Water Quality Control Act can accrue per day and per violation, and on a project that discharged through an entire wet season the totals add up quickly. The permit also requires that inspection and monitoring records be kept and made available, so a record you cannot produce is treated as an inspection that did not happen.
What to Do This Week
- Confirm every project disturbing an acre, or any part of a common plan that does, has a WDID number in SMARTS before grading starts.
- Name the QSP in writing and confirm they are doing the monthly inspection and reviewing every delegate’s inspection and sample.
- Check the risk level determination against current site conditions; a changed schedule or a newly listed receiving water can move a project to a higher level.
- Set up a forecast alert so the 72-hour pre-storm inspection is triggered automatically at the 50 percent, 0.5-inch threshold.
- For Risk Level 2 and 3 sites, verify sampling equipment, calibration records, and a designated trained sampler are on site before the first storm of the season.
- Walk the SWPPP site map against the actual site and have the QSD amend it where the layout, drainage, or phasing has changed.
- Audit the last 90 days of inspection records for gaps, and calendar the September 1 annual report.
If you need help building a SWPPP and keeping it current, or a review of a program that is already on a Regional Board’s radar, McNeil Safety Consulting can help. Learn more about our safety plan writing services or call (626) 546-9384.